Larimer/Weld counties
Larimer/Weld counties

We replaced natural gas pipeline in parts of Larimer and Weld counties and the new natural gas pipeline is now in-service. Work started in 2012 and was completed in 2014. Over the course of the project, we completed work in Berthoud, Fort Collins, LaPorte, Loveland and sections of unincorporated Larimer County.

Larimer County Mainline 2013 - 2014

We installed approximately 22 miles of new 16", high-pressure natural gas transmission pipe near Berthoud, and in Fort Collins, Loveland and unincorporated Larimer County. This work included tying over existing natural gas distribution stations to the new transmission line.

Fort Collins to LaPorte Lateral 2012

We installed approximately three-and-a-half miles of new, 6" steel natural gas pipeline from Vine Drive and Taft Hill Road to Overland Trail and Larimer County Road 54G.

Loveland to Greeley and South Loveland Lateral 2012

We installed approximately nine miles of 4" and 6" diameter natural gas pipeline along Colorado Highway 402 west of I-25, and east of I-25 along Larimer County Road 18 and Weld County Road 54.

Cement and Northern Laterals 2012

We installed approximately 13 miles of 4" and 6" diameter natural gas pipeline north of Fort Collins.